Key Takeaways
- Call 811 at least 48-72 hours before every excavation project; it’s legally required in all 50 states and initiates the coordinated utility marking process.
- 811 marks only public utilities; hire private locators for campuses, industrial sites, and commercial properties where owner-installed infrastructure exists.
- The tolerance zone (18-24 inches on either side of marks) is a no-mechanical-equipment zone; hand tools or vacuum excavation only within this buffer.
- Potholing verifies what marks cannot; physical confirmation of depth and exact location is required at utility crossings and high-risk zones before mechanical excavation begins.
- 76% of utility strikes are preventable; adherence to the locate-first workflow, verification procedures, and tolerance zone restrictions eliminates the vast majority of damages.
Utility locating establishes the foundation for safe excavation. Before any digging begins, locating identifies what’s buried and where, preventing catastrophic strikes that cause worker deaths, service outages, and multi-million dollar liabilities. This isn’t optional prep work; it’s the first mandatory safety control that anchors every decision that follows.
Without accurate utility locations, you cannot build a meaningful excavation plan, establish proper tolerance zones, or select appropriate digging methods. The stakes are extreme: $30 billion in annual U.S. strike costs, 39 worker deaths in 2022 alone, and 76% of all strikes preventable through proper procedures. This section covers what locating delivers, what it doesn’t, and why utility locating before digging must happen before the first shovel touches dirt.
What Is Utility Locating, And What Does It Confirm Before Excavation Begins?
Utility locating identifies the approximate horizontal position of buried facilities. Locators use electromagnetic detection, ground-penetrating radar, and utility records to map what’s underground, then communicate findings through painted marks, flags, maps, or locate tickets. Critical limitation: locating typically does not guarantee depth or exact positioning; it provides estimated locations that require verification.
Locating is a starting control, not a complete solution. In high-risk areas or congested corridors, physical confirmation through potholing or vacuum excavation is required before mechanical digging begins. Locating informs the excavation plan but never eliminates the need for hands-on verification when tolerance zones are approached.
What Should Readers Understand In 60 Seconds Before They Dig?
Assume these utility types may exist on any site:
- Electric power lines and conduits
- Gas/oil/petroleum/steam lines
- Communications/fiber optic cables
- Potable water mains
- Reclaimed water/irrigation systems
- Sewer/storm drain lines
- “Other/unknown” (abandoned lines, empty conduit, unrecorded facilities)
Public Locate vs. Private Locate
| Type | Who Performs It | What’s Typically Covered | What’s Commonly NOT Covered | Best Use Cases | Typical Deliverables |
| Public (811) | Utility company locators responding to one-call notification | Member utility facilities (electric, gas, water, sewer, communications owned by participating operators) | Private lines, site lighting, irrigation, customer-owned facilities, abandoned lines | Standard excavation on public right-of-way or when working near known public utilities | Painted marks, flags, 811 ticket number, approximate horizontal location |
| Private Locate | Independent locating contractors hired by property owner or excavator | Site-specific facilities, private utilities, owner-installed infrastructure, non-member utility lines | Lines not detectable by available technology, facilities with no records, utilities outside contracted scope | Campuses, industrial sites, commercial properties, areas with known private infrastructure | Marked facilities, method notes, sketch/map, photo documentation, confidence/limitations statement, optional GPS data |
Why Is Utility Locating The First Safety Control In Excavation Work?
Locating is first because it prevents high-consequence strikes and anchors the rest of the safe excavation planning process. Without knowing what’s below ground, excavators cannot perform meaningful Job Hazard Analysis (JHA), establish proper tolerance zones, or select appropriate excavation methods. Every subsequent safety decision, equipment selection, crew positioning, and emergency response planning depends on accurate utility information.
The data proves the point: $30 billion in annual U.S. strike costs and 76% of all strikes are preventable through proper locating procedures. Locating isn’t preparatory busywork; it’s the control that determines whether workers go home safe and projects finish on time and budget.
How Should You Explain The Safety And Business Case Without Over-Writing It?
Safety Impacts of Utility Strikes
- Electrocution/arc flash (energized electric)
- Fire/explosion (gas rupture)
- Asphyxiation (gas/sewer damage in confined spaces)
- Flooding/engulfment (water main breaks)
- Secondary hazards (traffic control, emergency response, exposed nearby utilities)
Critical stat: In 2022, 39 workers died in trenching/excavation incidents (+160% vs. prior year). Many are preventable with strong locating + damage prevention.
Business Impacts After A Strike
- Outages (power/telecom/water impacts to customers and communities)
- Direct repair/restoration costs
- Delays (stop-work, resequencing, schedule extensions)
- Regulatory action (inspections, stop-work orders)
- Liability/claims (property + third-party damage)
- Reputation/contract risk (future work, bonding)
Economic reality: $1 in direct repair often triggers $29 in indirect/social costs.
Why Strikes Still Happen Even After Calling 811
- Inaccurate marks (interference, locator error, hard-to-detect lines)
- Private lines not included in one-call systems
- Expired tickets (work continues past validity)
- Scope changes without a new locate request
- Weak white-lining/pre-marking
- Congested corridors (overlapping marks, multiple depths)
- No verification/daylighting before mechanical excavation
What Does OSHA Require When Excavations Approach Underground Installations?
OSHA standard 29 CFR 1926.651(b) establishes the compliance baseline: “The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation.”
This places legal responsibility on employers to identify and manage underground utility risks before breaking ground. The standard further requires determining exact locations by “safe and acceptable means” when excavation approaches these installations. Tolerance zone requirement: The typical tolerance zone is 18 to 24 inches on either side of the outer edge of the marked line, within which only non-mechanical excavation methods are permitted.
What Does “Safe And Acceptable Means” Look Like On A Real Jobsite?
“Safe and acceptable means” translates to physical verification before mechanical excavation begins. OSHA’s requirement isn’t satisfied by painted marks alone; it demands confirmation through non-destructive methods when approaching buried utilities. This verification closes the gap between approximate marking and actual facility location.
Verification examples in practice:
- Daylighting/potholing at utility crossings before mechanical excavation
- Hydro vacuum excavation (hydrovac) for non-destructive exposure
- Careful hand exposure using shovels and non-powered tools where appropriate
- Controlled exposure at critical utility crossings
- Escalation to engineering review when conflicts appear between marks and excavation plan
What Documentation Proves You Followed A Locate-First Process?
Records to keep:
- ☐ 811 ticket number + submission and expiration dates
- ☐ Positive response confirmations from all notified utility operators
- ☐ Photos of marks on ground + offset measurements from fixed references
- ☐ Pre-job briefing attendance and safety topics covered
- ☐ Verification/daylighting notes with locations and findings
- ☐ Documentation of scope changes and re-mark requests
- ☐ Incident/near-miss logs with corrective actions
What Do 811 “Call Before You Dig” Tickets Actually Do, And What Don’t They Do?
The 811 system initiates coordinated notification to participating utility operators. Dialing 811 triggers a legal obligation for member operators to mark the approximate location of their buried lines within the planned excavation area. This notification is mandatory 48 to 72 hours before any project begins, required by law in all 50 states.
What 811 doesn’t do: It’s not a guarantee that all buried lines are covered. Private utilities, abandoned facilities, and non-member operator lines will not be marked through the 811 system. Excavators remain responsible for identifying these facilities through underground utility locating services or other means.
How Do You Confirm Every Utility Has Responded Before You Dig?
Readiness gate checklist:
- ☐ 811 ticket submitted with correct excavation area and details
- ☐ All notified operators have responded (positive response received)
- ☐ Marks on ground match excavation scope and work area
- ☐ Conflicts between marks and excavation plan resolved
- ☐ Crew briefing completed covering marked utilities and tolerance zones
- ☐ Verification plan established for high-risk zones and utility crossings
What Private Facilities Are Commonly Missed If You Rely On 811 Alone?
Facilities not covered by 811 notification:
- Site lighting systems and outdoor illumination circuits
- Irrigation systems and landscape water lines
- Private power feeders to buildings and structures
- Campus/industrial distribution networks
- Owner-installed communications and data networks
- Security systems and access control wiring
- Temporary utilities from prior construction phases
What Do Utility Markings Mean, And How Should Crews Interpret Them?
Marks communicate “facility presence + approximate location,” not safe-to-dig clearance. The mark indicates where a utility is believed to exist horizontally but provides no guarantee of depth or exact position. Locating technology has limitations, signal interference, non-metallic materials, and congested corridors all affect accuracy.
Marks are the starting point for safe excavation, not the endpoint. They define where caution is required and where verification must occur before mechanical digging begins. Treat every mark as a warning flag that triggers additional investigation, not as permission to excavate.
How Should You Teach Mark Literacy Fast (Without A Wall Of Text)?
Crews need instant recognition of what each color means and why it matters. The APWA Uniform Color Code is the industry standard across North America; memorizing these colors is non-negotiable for anyone operating excavation equipment or working in trenches. Color recognition prevents confusion, enables proper tolerance zone identification, and supports rapid emergency response when utilities are exposed.
APWA Uniform Color Code
| Color | Typically Indicates | Common Field Examples |
| White | Proposed excavation limits | Pre-marked work area boundaries, trench alignment |
| Pink | Temporary survey markings | Survey control points, property boundaries |
| Red | Electric power lines, cables, conduit | Transmission lines, service laterals, lighting circuits |
| Yellow | Gas, oil, petroleum, steam | Natural gas distribution, propane, fuel oil, steam heating |
| Orange | Communications, cable TV, fiber | Telephone, cable TV, fiber optic, alarm systems |
| Blue | Potable water | Water mains, service lines, fire hydrant supply |
| Purple | Reclaimed water, irrigation | Non-potable reuse systems, landscape irrigation |
| Green | Sewer and drain lines | Sanitary sewer, storm drains, catch basins |
Tolerance zone essentials:
- Definition: The legally defined space extending 18-24 inches on either side of a marked utility line
- Why it exists: Marks show approximate location; actual utility position can vary within this buffer zone
- Risk level: Treat as a high-risk area, no mechanical equipment permitted
- Verification expectation: Physical confirmation (potholing/daylighting) required at crossings and for critical utilities
- Excavation method: Hand tools or vacuum excavation only within tolerance zone boundaries
When marks are missing/faded/conflicting:
- Stop work immediately in the affected area
- Protect the area from traffic and other site activities
- Request re-mark by calling 811 again (document ticket number)
- Re-pre-mark (white-line) if excavation limits have changed
- Escalate to private locate service or verification if marks remain unclear
- Document the delay, reasons, and resolution in project records
How Do You Run A Locate-First Excavation Workflow From Planning To Backfill?
A locate-first workflow only works if each step is completed in order; skipping steps breaks the chain.
10-Step Workflow
- Scope review: Plans, site history, surface indicators (valves/meters/junctions)
- White-line: Mark proposed dig limits (white paint/flags)
- Submit 811: Send accurate limits + job details
- Wait window: Protect markings, maintain access during 48–72 hrs
- Confirm responses: Ensure every notified utility replied
- Walkdown: Compare marks to plan; flag conflicts
- Daylight/pothole: Verify crossings + other high-risk points
- Excavate with controls: Hand/vac in tolerance zone; mechanical only outside
- Maintain marks: Inspect daily; request re-marks as needed
- Closeout: Record actual utility locations + near-misses/lessons learned
Pre-Dig “Go / No-Go” (All Must Be TRUE)
- Valid, active 811 ticket (in date range)
- All operators responded
- Marks visible/legible and cover the work area
- Tolerance zones identified + communicated
- Potholing/daylighting completed at required locations
- Crew briefed on locations, methods, emergencies
- Operators understand tolerance restrictions
- Emergency contacts posted (utilities + 911)
What Locating Technologies Are Used, And What Are Their Limitations?
Different technologies excel in different conditions. Site characteristics (soil type, moisture, congestion) and utility materials (metallic vs. non-metallic) significantly affect reliability. No single technology works perfectly in all situations; understanding strengths and limitations guides proper technology selection and prevents over-reliance on any one method for utility mapping and detection.
Technology Comparison
| Technology | Best For | Weak When | What You Get | Common Failure Modes | When to Choose It |
| EM Locator | Metallic utilities (copper, steel, iron) in open areas | Non-metallic pipes (PVC, HDPE), congested areas with signal interference | Horizontal trace of conductive utilities, approximate depth reading | Signal bleeding to adjacent metal, inaccurate depth on deep/parallel lines | Standard first-pass location for gas, water, electrical conduit |
| Ground Penetrating Radar (GPR) | Non-metallic utilities, concrete-encased conduit, general subsurface mapping | Wet/clay soils, highly conductive ground, very deep utilities (>15 ft) | Subsurface profile showing anomalies and reflections | Interpreting complex data, differentiating utilities from other buried objects | Verifying non-metallic lines, locating in congested corridors |
| Vacuum Excavation/Daylighting | Physical verification, exposing exact location and depth | None, most reliable method but slower and more costly | Visual confirmation of utility type, size, depth, and horizontal position | Limited to point locations (not continuous tracing), requires surface access | Final verification before mechanical excavation, utility crossings, critical infrastructure |
What Are The Most Common Root Causes Of Utility Strikes, And How Do You Prevent Each One?
Most strikes come from repeatable failures. Use the warning signs below to intervene early, before damage occurs.
| Root cause | Early warning sign | Preventive control | Field check | Escalation action |
| No 811 notification | No ticket on file / rushed start | No ticket, no dig (company-wide) | Confirm ticket is posted before equipment arrives | Stop work → submit 811 request → document delay |
| Inaccurate marks | Marks don’t match meters/vaults/known features | Pothole/daylight at crossings + high-risk areas | Compare marks to as-builts + surface indicators | Request re-mark → use private locator if needed |
| Scope changed | Dig extends beyond white-line limits | Update 811 ticket when limits change | Confirm marks cover the active excavation zone | Submit new locate for expanded area |
| Expired ticket | Work continues past validity (often 14–28 days) | Track expirations; renew before lapse | Review ticket dates in daily toolbox talk | Stop work → renew ticket → document gap |
| Private lines not located | Commercial/campus sites; lots/lighting | Use private locator on non-residential sites | Ask owner about private utilities before digging | Bring private locator mid-job if suspected |
| Skipped verification | Schedule pressure; potholing skipped | Require potholing at every crossing | Supervisor spot-check before mechanical excavation | Stop mechanical excavation → verify → retrain |
| Poor crew briefing | Confusion on color codes/tolerance zones | Daily toolbox talk on locations + safe dig plan | Quick crew check on tolerance/hand-dig rules | Remove unqualified operators → refresher training |
| Mark destruction | Faded/removed flags; weather/traffic/trades | Inspect daily; request re-mark when unclear | Stop if marks are illegible in the work zone | Protect area → emergency re-mark → document delay |
What Should You Do If You Expose, Contact, Or Damage A Utility?
Priority is always: stop work → secure → protect people → notify.
Immediate response (memorize):
- Stop work in the affected area
- Secure/cordon off the area (prevent additional contact/public access)
- Evacuate if needed (gas, electric, confined-space risk)
- Eliminate ignition sources when applicable (gas/petroleum)
- Notify the utility owner/operator (use 811 emergency contact)
- Call 911 if there’s fire, injury, explosion risk, or imminent public danger
- Protect the public (perimeter, traffic control, notify adjacent properties)
- Document (ticket #, exact location, photos, witnesses)
Have ready when calling the utility:
- 811 ticket number + locate date
- Exact location (address/cross streets/GPS)
- Utility type (color code/visual ID)
- What happened (equipment, depth, type of contact)
- Current condition (leak/energized/pressurized/exposed)
- Photos of marks + damage
- On-site contact name + phone
- Whether any emergency condition exists
What Scenarios Require Extra Locating Rigor Beyond The Standard Process?
Use enhanced verification when conditions make standard locating less reliable:
- Trenchless/HDD: limited access along bore path; multiple corridor crossings
- Congested corridors: dense/overlapping utilities (common in urban areas)
- Deep excavation: beyond typical utility depth (e.g., >10 ft)
- Demolition/mass grading: high chance of abandoned/unknown lines
- Emergency excavation: time-critical work with shortened notice
- Paved/snow-covered surfaces: marks obscured or impossible to place
- Uncertain mapping: missing/conflicting/inaccurate as-builts
- Repeated re-marks: inconsistent or unclear locate results
How Do You Decide When To Hire A Private Utility Locator?
Private locators fill the gap between what 811 covers and what actually exists underground. Commercial properties, campuses, and industrial sites typically have extensive private infrastructure that won’t appear on 811 marks. Waiting until mid-project to discover unmarked lines causes expensive delays, hiring a private utility locating service during planning prevents this.
Signals that suggest private lines are likely:
- Campuses (universities, hospitals, military bases) with internal distribution networks
- Industrial sites with process piping, plant utilities, and inter-building connections
- Large commercial parcels with multiple buildings and site improvements
- Extensive site lighting, security systems, or irrigation infrastructure
- Owner-installed upgrades (solar arrays, generators, telecommunications equipment)
- Inconsistent or missing as-built drawings in project documents
- High-density communications corridors (data centers, telecom hubs)
Deliverables required from private locate service:
- ☐ Marked facilities in the field using paint/flags with method notes
- ☐ Sketch or site map showing located utilities and tie-in points
- ☐ Confidence level statement and limitations of the locate (areas not accessible, utilities not detectable)
- ☐ Photo log documenting marks and field conditions
- ☐ Offset measurements and tie-ins to fixed reference points
- ☐ Optional: GPS coordinates or GIS-compatible data file
- ☐ Re-mark policy (will locator return if marks are destroyed?)
What Should Your Final Pre-Dig Checklist Include To Make Locating The True First Step?
This is the last gate before digging. If any answer is No, don’t excavate.
5 Go/No-Go Questions (All Must Be YES)
- Valid 811 ticket for the current work area and within the date range?
- All utility operators responded (positive response/clearance)?
- Marks are legible and match the scope + surface indicators?
- Potholing/daylighting completed at required crossings/high-risk zones?
- Crew briefed on locations, tolerance zones, hand-dig areas, and emergency steps?
What To Standardize On Every Job
- No ticket, no dig (zero exceptions)
- White-line every excavation area 24 hrs before the 811 call
- Clear potholing triggers (crossings, congestion, critical utilities)
- Daily mark checks + re-marks when unclear
- Document everything (photos, tickets, verification log)
- Escalation playbook (unclear marks, scope changes, private lines)
- Post-job review (near-misses + lessons learned)
Making Utility Locating The Foundation Of Every Excavation Project
Locating isn’t paperwork; it’s the safety and cost-control foundation. Treat it as step one: call 811, verify by potholing, enforce tolerance zones, document, and escalate early. Crews that do this consistently prevent strikes, reduce liability, and protect schedule and reputation.
Need expert utility locating services for your next project? Contact Bess Utility Solutions to ensure your excavation starts safely and stays safe from day one.

